Office fit-out hero
Project X9 — Bristol

Interior fit-out: commercial workspace transformation

Complete design & delivery for 1,200 m² office fit-out in Bristol — space planning, MEP coordination, bespoke joinery and FF&E procurement tailored to contemporary workplace needs.

Plan overview

Project overview

Plaleno delivered turnkey fit-out works for a tech client in Bristol, combining interior architecture, acoustics, lighting design and client-specific joinery. Emphasis on flexible meeting clusters, wellbeing zones and durable finishes for high-traffic areas.

  • Client: Confidential (tech sector)
  • Area: 1,200 m² across two floors
  • Programme: 14 weeks design + 12 weeks delivery

Key outcomes

  1. Improved capacity and circulation
  2. Acoustic meeting pods and quiet booths
  3. Sustainable material selection and waste minimisation

What we delivered

Interior Architecture

Ceiling strategies, partitions, and interface detailing with MEP for smooth installation and sign-off.

FF&E & Joinery

Bespoke reception desk, benching joinery, integrated storage and meeting pod cladding.

Lighting & Acoustics

Layered lighting design with dimmable scenes and acoustic treatments tuned for speech privacy.

Process & milestones

1. Briefing

Stakeholder workshops, site surveys and budget alignment.

2. Concept

Layouts, material palettes and FF&E concepts for client review.

3. Technical

Construction drawings, MEP coordination and approvals.

4. Delivery

Principal contractor management and snagging to handover.

Case study: Fit-out highlights

For Project X9 we delivered a resilient workplace solution prioritising flexibility and wellbeing. Notable items included acoustic pods designed for hybrid meetings, a timber-clad reception to reflect brand warmth, and a reconfigurable breakout allowing for events.

  • Cost control through early procurement and modular joinery.
  • Short programme delivered via phased handovers.
  • Post-occupancy survey and minor adjustments included.
Case study image

Project team

Lead designer

Ava Thompson — Lead Interior Architect

Responsible for architecture coordination, FF&E selection and site supervision. Ava specialises in commercial workplace strategies and resilient material systems.

Frequently asked

Programme varies by scope — the X9 project was delivered in a 12-week construction phase following 14 weeks of design. Early engagement reduces programme risk.

Yes — Plaleno offers principal design coordination and contractor management services through delivery to practical completion and handover.

We provide phased cost planning and can deliver fixed-price packages where full scope and specification are agreed before procurement.